SCC: Dairy Farm in Syanno district not completed due to the fault of the general contractor

Dairy farm in Syanno district still has not completed due to the fault of the general contractor, the press service of the State Control Committee. Orsha mezhrayotdel Financial Investigations of the Committee of State Control in the Vitebsk region revealed facts of abuse of authority by the Director of the State Construction Company.

As the general contractor for the construction of a dairy farm in Syanno district, in 2012, the company received more than Br500 million targeted advances to pay for concrete products (slabs). Money has been spent through credit line at the bank to the customer for the construction.

Despite this at the direction of the Director-building enterprise that amount sent for other purposes - for repayment of debt and interest on previous loans, payment of wages and contributions to the Social Security Fund.

As a result, the object that is being built, is still not delivered all the slabs, and thus dairy farm in operation has not been introduced. Thus, the actions of the Director of the building enterprise caused substantial harm to the public interest.

According to the prosecutor's office, Orsha district instituted criminal proceedings under Part 2 of Article 424 (abuse of power or authority) of the Criminal Code of the Republic of Belarus. The maximum penalty under this heading provides for imprisonment for up to six years with deprivation of the right to occupy certain positions or engage in certain activities. Currently, in a criminal case to a preliminary investigation.

belta.by